In some cases, the resource usage for the date of Change Order placement may look to be billed twice, but it is not. Consider the following example.

  1. A customer has a subscription with a resource overused. The customer places a Change Order to switch the subscription's service plan. In this Change Order there will be the following detail:

    Resource overuse for the period from <Last billing date> to <Date of CH order placement>.

  2. On the subscription's next billing date the subscription will be billed, and in the Billing Order details there the customer will see the following detail:

    Resource overuse for the period from <Date of CH order placement> to <Date of Billing>.

    And this looks like the customer is billed twice for this date: <Date of CH order placement>.

    Actually, the overuse in this case is calculated as follows:

    • In the Change Order, the resource overuse is collected for the period from <Last billing date 00:00> to <Date of CH order placement exact time>.
    • In the Billing Order, the resource usage is collected for the period from <Date of CH order placement exact time> to <Billing date 00:00>.

    This way, resource usage is collected for exactly 1 month.